Crescent Kashmir

Power shutdown

Decrease Font Size Increase Font Size Text Size Print This Page

SRINAGAR, SEPTEMBER 23: According to the Power Controller, Kashmir Province, in order to carry out branch cutting and stabilization of 33 KV Gopalpora Pahalgam line, the power supply to the areas fed from the said line and falling under Receiving Stations Hutmurrah, Salia, Sallar, Ashmuqam and Pahalgam shall remain affected on September 24 from 10 am to 5 pm.

The power supply to the areas fed from the said line and falling under Receiving Station Pahalgam shall remain affected on September 26 from 10 am to 5 pm.

Similarly, the shutdown of 33 KV Lissar Dooru line shall be taken as the ground clearance of said line has got reduced below prescribed standards at many places, the power supply to the areas fed from the said line and falling under Receiving Stations Dooru, Hillar, Dooru Nowgam shall remain affected on September 24 from 9 am to 5 pm.

Also, to carry out installation and charging of 25 MVA Power Transformer, shutdown of 132/33 KV Lassipora GS shall be observed on September 27 from 10 am to 4 pm.

Leave a Reply

Your email address will not be published. Required fields are marked *