Advisor Baseer Khan reviews preparedness of KPDC for 2nd spell of snowfall in Valley

Decrease Font Size Increase Font Size Text Size Print This Page

SRINAGAR, JANUARY 22: Advisor to Lieutenant Governor, Baseer Ahmad Khan, today held a review meeting with Kashmir Power Development Corporation regarding preparations being put in place by the Corporation to deal with second spell of snowfall in the Kashmir Valley.

The meeting was attended by MD, KPDCL, Ajaz Assad, Chief Engineer, Power Distribution, Ajaz Ahmad and Chief Engineer, Transmission, Hashmat Qazi besides other concerned.

Advisor Baseer Khan enquired about the available stock of transformers, wires, deployment of enforcement staff and related necessities. He asked the officers to keep contingency plan ready for restoration of electricity supply within the stipulated time of 24 hours in urban areas and 48 hours in rural areas.

Advisor was informed that the department is fully prepared to tackle any issue including erection and replacement of damaged electric poles besides repairing and maintenance of supply lines and transfers in the wake of possible snowfall season. He said that the department has successfully restored power supply in stipulated time during the first heavy snowfall span of the season.

Advisor was further informed by Chief Engineer that sufficient stock of transformers, poles and wires is available to solve any issue of power restoration. Besides, adequate men and machinery is in a standby mode while enforcement staff is executing work on war footing basis.

Regarding status of augmentation and installation of transformers at Grid Station Delina, Advisor was informed that all the works have been completed barring arrival of transformers. Besides, three transformers are being shifted from GSS Budgam of which one has arrived at the site while two others are in transit.

Advisor was further informed that erection and stringing work on construction of 220KV D/C Wanpoh-Mirbazar Transmission line is under progress and expected to be completed in first week of February 2020.