PMDP projects are in progress in various parts of Jammu and Kashmir and being under execution the government of Jammu and Kashmir has been closely monitoring these projects.

In this direction recently the Chief Secretary reviewed PMDP projects in Jammu and Kashmir.

He directed completion of various infrastructural works within the stipulated timelines

Out of 53 PMDP projects, 21 projects have been completed while another 10 projects will be completed by the end of the current fiscal year.

While reviewing the construction of Semi Ring Road, Srinagar the Chief Secretary directed the Public Works Department to explore the feasibility of constructing a take off point at Pandach so that the issues of relocation of 199 shops and the land acquisition that may result due to the present alignment are effectively dealt with.

He directed the department to expedite the work on various packages on Jammu-Akhnoor road by liasoining with the army authorities wherever necessary so that the original timelines are adhered to.

Work on Chenani Sudhmahadev road is going on briskly and the geo-technical surveys of three tunnels on this road are being completed and once sanction to the construction of these tunnels is received, work will pick up pace.

He directed the department to take steps, including coordinating with the law enforcement agencies, to ensure that Sinthan pass road may be kept in functional condition.